|
Page
two
Continued....
PARLIAMENTARY STATEMENT BY MINISTER OF ENERGY
HONOURABLE JOSEPH KOFI ADDA (MP),
ON THE CURRENT ENERGY SITUATION IN GHANA
MEDIUM AND LONG TERM PROJECTS
Mr. Speaker, in order to ensure that adequate
generation capacity is available to meet the medium
term requirements of the country, the Ministry of
Energy is in the process of procuring additional
power plants to be installed in the next 12 –18
months. This forms part of the plan to have an
installed capacity of over 3,000 MW by 2010. This
programme will result in a substantial increase from
the current installed capacity of 1,730 MW.
Mr. Speaker, the objective of the medium term
programme is to develop sufficient generation
reserves to ensure that the country does not go
through this experience again in the future. The
projects currently being implemented by the Ministry
of Energy are: 220 MW power plant procured from
ALSTOM of Switzerland . This plant is expected to be
operational by September, 2008. The plant will be
converted into a 330 MW combined cycle plant in the
future.
Again there is a 84 MW power plant procured from
Ranhill of Malaysia. This is expected to be
operational in July, 2008. Operationalisation of the
125 MW Osagefo Barge in 2008/9
The implementation of the 400 MW Bui hydroelectric
power plant. Construction work is expected to
commence in the 3rd quarter of 2007 and is scheduled
for completion in 2011/2012.
The addition of 110 MW to convert the Takoradi
International Company (TICo) plant to a Combine
Cycle plant in 2009.
GENERATION BY INDEPENDENT POWER PRODUCERS (IPP's)
Mr. Speaker, Members of this august house, the
Ministry of Energy is implementing a policy to allow
Independent Power Producers (IPPs) to develop and
operate power plants in the country. The objective
is to allow the private sector to support part of
the investment requirements of the power generation
sector. This will enable the Government deploy the
resources that would otherwise have been used for
power generation for other sectors such as health,
education, road etc.
Mr. Speaker, in order to facilitate the entry of the
IPPs, a new company, the Ghana Grid Company has been
set up to be responsible for the operation of the
transmission sector which hitherto was the
responsibility of the VRA.
Further, Mr. Speaker, the Ministry of Energy has
received proposals from a number of IPPs who are in
the process of establishing power plants in Ghana .
These are:
* CenPower - 300 MW
* Shenzhen group - 200 MW (PPA with ECG)
* GECAD - up to 300 MW
* Ranhill Consortium - up to 300 MW
* Brazilian Consortium up to 300 MW
* Ranhill of Malaysia - up to 300 MW
The Ministry of Energy is facilitating the
development of these projects.
WASTE TO ENERGY POWER PLANT
Mr. Speaker, construction work has recently started
on the first waste to energy plant in Kumasi . This
will produce up to 50 MW of electricity from the
combustion of municipal waster collected in the
Kumasi metroplis. The project is planned for
completion in 2008.
IMPROVEMENT IN THE POWER DISTRIBUTION SYSTEM
Mr. Speaker, as part of the arrangements to improve
the delivery of power to consumers, the Government
has made an allocation of 300 billion cedis in the
2007 Budet to Electricity Company of Ghana (ECG) to
support critically needed investments in the power
distribution sector. These projects when completed
will result in a significant improvement in the
operations of the ECG.
The sector has also been allocated US$ 172 million
in the 2007 budget to enable them carry out other
improvements required in the power system.
OTHER RELATED ISSUES
Mr. Speaker, with your kind permission, I wish to
turn my attention to some major issues that have
been debated in the public domain in recent times so
as to give my honourable colleagues and the general
public a sense of the government’s position on them
or the status of development in those areas.
· Investment in the Energy Sector
Mr. Speaker, it is been said in certain circles that
this Government has not invested substantially to
augment generation capacity in the country. The
context within which this is said should always take
into consideration how President Kufuor’s
administration started its tenure. Any objective
analyst would not fail to appreciate the fact that a
country heavily burdened in debt, would be severely
constrianed in terms of making significant
investments in all areas of the economy at the same
time within a comparatively short in office. Mr.
Speaker, it was not too long ago when as a nation we
adopted the HIPC initiative because of huge debts
that hung on our necks at the time. Manifestly, at
the outset, the New Patriotic Party’s administration
faced these serious investment constraints.
Mr. Speakers, had it not been for the prudent and
pragmatic decision by His Excellency President John
Agyekum Kufuor to take the HIPC path, we probably
would not be having the benefits of multi donor debt
relief today to be able to acquire some of the
generating plants that we are procuring now.
Mr. Speaker, that not withstanding, one can list the
completion of retrofitting that added 108 MW to
Akosombo, the investment in the West African Gas
Pipeline that is now attracting IPP investors in the
energy sector. The ability of this government to pay
demurrage and invest in the pond construction as
well as other related costs to facilitate the
bringing down of the Osagyefo Barge which had been
rotting away in Italy, as well as the Performance
Enhancement of the Takoradi Termal 1 Power Station
are also other examples of financial outlays by the
NPP administration led by His Excellence President
Kufuor.
Mr. Speaker, to conclude on the investment issue,
let me state that we just got out of HIPC, we are
now getting our debts cancelled. We are barely two
years into this chapter of debt cancellation and my
appeal is that Ghanaians should exercie a little bit
of patience. Before long, the fruits of the NPP
government’s endeavours will become crystal clear.
· VALCO
Mr. Speaker, a lot has been said about VALCO and the
view of some seems to be that we should not own that
vital asset or that we should not give Ghanaians
jobs.
Mr. Speaker while others may have the right to their
own views let me remind this Honourable House that
during the two previous load shedding programmes I
referred to in the eighties and nineties, VALCO was
out of commission before the programmes started.
This means that the situation then would have been
worse off than it is now if VALCO was running at
these various times. In our time, we bought back
VALCO, put people to work and sold products
globally. In mu view the power was well used. It is
unfortunate that VALCO had to be shut down. In any
case Mr Speaker, I am glad to announce that VALCO is
exploring its dedicated source of power to enable it
resume operations and that the government of the NPP
would assist it so that we can get Ghanaians
employed and run the asset to our benefit as a
nation.
· West Africa Gas Pipeline Project
Mr. Speaker, the Government of the New Patriotic
Party has dedicated US$118 million of investible
funds into this project to help increase generation
capacity due to the relatively lower cost of gas as
opposed to other fuels. This project will definitely
add on to the generating capacity of the country.
Mr. Speaker, the laying of the pipelines as well as
the cross-shoring pipes work have been completed and
the metering and regulating stations would be ready
soon. The necessary regulatory instruments to
facilitate operationlization of the secondary gas
market are at the Cabinet stage and should be coming
to this august House soon. It is expected within the
next three to four months that the first
uncompressed flow of the gas would occur, with the
compressed gas to follow soon thereafter.
· TICO Expansion Project
Mr. Speaker, it is a fact that if the TICO expansion
were undertaken, we would have an addition 110 MW
through the combined cycle machanism. However, the
Government did not consider the cost presented by
our then partners as acceptable. Simply put, we did
not thank it wise to pay US$110 million for 220 MW
and now have to pay US$215 million for only 110 MW.
The delay resulted from our search for acceptable
financing to carry out this expansion. We were also
of the viewthat we would be paying for a project
that would raise the value of the asset only for it
to be sold a premium by our partners. Today, we are
vindicated as our partners did not regard even the
soverignty of our country when they sold their stake
to TAQA, an Abu Dhabi Company without offering us
the first right of refusal. The matter has been
taken up seriously and every effort would be made to
ensure that we are not only treated fairly but that
we would get our due share and still get additional
generation capacity from the venture. As I speak,
Mr. Speaker, there are plans to even expand this to
1,000 MW.
· Osagyefo Barge
Mr. Speaker, the much advertised movement of the
Barge to Tema has not taken place because we missed
the weather window last year due to prolonged
negotiation to get reasonable funding for that move.
As we speak, a number of companies have expressed
interest in operating the barge where it is and we
are in negotiations with them and hope this would
happen in the course of the year.
· Nigeria
Mr. Speaker, the President, His Excellency, J.A.
Kufuor, requested the Government of Nigeria in
February, 2007, to supply up to 80 MW to Tog/Benin.
This request was within the framework of the West
African Power Pool (WAPP). The objective was for
Ghana to “claw back” 80 MW which it contractually
supplied to Togo/Benin.
Mr. Speaker, this arrangement has been fulfilled and
Nigeria currently supplies Togo/Benin with 70-80 MW
of electricity. The VAR has consequently reduced its
power supplies to Togo/Benin thereby making more
power available to Ghanaians.
Mr. Speaker, the direct supply of power from Nigeria
to Ghana will be dependent on the resolution of the
technical issues regarding the joint operation of
the two power systems.
Mr. Speaker, a technical team from Ghana is
currently in Cotonou, Benin assisting their Nigeria
and Beninois counterparts to resolve the problem. It
is my understanding that they are close to a
solution.
· La Cote d’Ivoire
Mr. Speaker, the arrangement with La Cote’dIvoire
for the supply of 120 MW of power did not
materialize as they had difficulties with their
power facilities and the natural gas infrastructure.
The Ivorians are currently in the midst of a load
curtailment programme as stated earlier and are
therefore unable to supply us the required levels of
power to help us in this time of need.
· Togo and Benin
Mr. Speaker, we have been compelled by the
circumstances to withdraw a substantial level of the
power we supply to Togo and Benin. Out of a total of
80 MW, we are now giving them only 20 MW essentially
to Togo while Nigeria is supplying power to Benin
through a special ‘looping’ arrangement and not
through the transformer system.
· Rural Electrification
Mr. Speaker, let me also assure this house that
based on the confidence of this government that
there will be adequate generation in the near
future, we are continuing with the rural
electrification and indeed would even endeavour to
speed it up while also working on intensification of
distribution in the urban areas.
CONCLUSION
Mr. Speaker, it is clear from earlier sections of
this statement that this is not the first time that
Ghana is going through a load shedding arrangement.
Indeed the past ones were more severe than this one.
Mr. Speaker, as I have enumerated, the Government is
tackling the energy crisis with all the seriousness
that it deserves. The Government has also committed
substantial funds to support the resolution of the
energy problem. While some of my colleagues may
continue to make political capital out of the
current energy situation, we firmly believe we are
on top of the situation and are confident we shall
be out of it within the next three to four months if
all things go as planned.
Mr. Speaker, the government has a very clear and
effective programme to deal with this situation in
the Short, Medium and Long Term. The programme is
backed by a policy and Energy Strategic Plan to lead
the country into the future and guarantee OUR FUTURE
ENERGY SECURITY. We are confident that the policy of
becoming self-sufficient in our energy supply
requirement and eventually becoming a net exporter
will be a successful one.
Mr. Speaker, within six years in office, the NPP
government has invested substantial funds in the
energy sector and we are convinced that within the
next two to three years, Ghana would be in a
position to ensure that this situation does not
recur again.
Thank you, Mr Speaker for this opportunity.
Kweku Asare, Accra, June 23, 2007, Ghanadot
.....Previous
page |